24 June 2008

10 March 2008

lounge

bed room

bath room
21 February 2008

lounge

bathroom
14 February 2008

Lounge

bathroom
12 February 2008

lounge

bathroom
11 February 2008

Bathroom
6 February 2008

bathroom
3 February 2008

Lounge
29 January 2008

Lounge
23 January 2008
s
Lounge
22 January 2008

Lounge
16 January 2008

Lounge (currently used as site office by the builders)

bedroom

Bathroom
10 January 2008

16 December 2007

bedroom
11 December 2007

staff lounge
8 December 2007

bathroom
5 December 2007

bathroom
4 December 2007

bed room
26 November 2007

New staff flat: lounge

New staff flat: bath room
25 November 2007

New staff flat (bed room)
23 November 2007
New staff flat: bed room
New staff flat: bath room
New staff flat: lounge
7 November 2007

New staff flat: bath room
3 November 2007

New staff flat: bedroom

New staff flat: bathroom
31 October 2007

New staff flat: lounge

New staff flat: bathroom
18 October 2007

new staff lounge
11 October 2007

the new staff flat: bedroom

The new staff flat: lounge
9 October 2007

New staff flat: bath room and bed room
2 October 2007

New staff flat: lounge
26 September 2007

The new staff flat: bedroom (left) and lounge (right)
20 September 2007
The new staff lounge
The new staff bath and bed room
12 September 2007
The new HAART Clinic (ground floor), administration section (1st floor) and Blessed Gérard's Children's Home Extension (2nd floor)
3 September 2007
The new HAART Clinic (ground floor), staff flat and administration section (1st floor) and Blessed Gérard's Children's Home Extension No. 1 (2nd floor, the walls starting to be built)
The new Staff flat
30 August 2007

Building site overview


29 August 2007

The new staff flat
28 August 2007

The new staff flat

The meditation room (back) and staff flat (front)
27 August 2007

Blessed Gérard's Church will be the only part of the original building (opened in 1996) which will still be visible from outside.
All other parts of the building have been extended over the years (1st extension in 2000, 2nd extension in 2002)

The new HAART Clinic (ground floor) and the new administration and staff accommodation section (1st floor)
20 August 2007

Overview of our building site

The HAART Clinic (ground floor) and Administration section (1st floor)

The new staff flat
18 August 2007

The new administration section outside

The new staff flat
16 August 2007

The new administration section
15 August 2007

The new administration section is at ceiling height.
14 August 2007

The walls in the new administration and staff accommodation sections being built.
8 August 2007

The first floor above the HAART Clinic is still growing
7 August 2007

The new administration and staff accommodation section above the HAART Clinic is taking shape.
6 August 2007

The walls of the first floor above the new HAART Clinic are going up to provide more space for offices and staff accommodation.
2 August 2007

The walls for the new staff accommodation and offices are going up.
1 August 2007

The floor slab on top of the HAART Clinic is cast

The new HAART Clinic
31 July 2007

The floor slab on top of the HAART Clinic being cast.
30 July 2007

Everything is prepared for the floor slab on top of the HAART Clinic to be cast.